Energy Secretary Garin Commends Negros Power For Rapid Post-Typhoon Tino Restoration

Energy Secretary Sharon Garin has commended Negros Power and the communities of Central Negros for their rapid and coordinated efforts in restoring electricity following the severe impact of Typhoon Tino. The Signal No. 4 typhoon, which struck on November 4, 2025, caused widespread outages across the region, prompting an extensive restoration campaign marked by teamwork, preparedness, and community support.
Secretary Garin described the response as a strong display of resilience, emphasizing that the combined efforts of utility crews, local officials, and residents played a crucial role in speeding up recovery. Her statement underscored how the unity between Negros Power and the public contributed to the restoration of essential services in a relatively short period.
Major Restoration Milestones
Three weeks after the typhoon’s landfall, Negros Power reported substantial progress. As of 11:00 AM on November 21, 2025, all major components of the distribution system had been fully restored:
- 5 out of 5 sub-transmission lines energized (100%)
- 11 out of 11 substations operational (100%)
- 48 out of 48 feeders restored (100%)
In Bacolod City — home to 157,646 customers — the restoration status demonstrated notable completion:
- 100% of secondary lines brought back online
- 99.48% of metering and service-drop connections restored
- Only 812 customers, or 0.52%, remained for final re-energization
Across Negros Power’s entire franchise area, covering 244,915 affected consumers, the company successfully re-energized 96.50%, leaving 3.50% pending. The remaining areas were primarily those in remote locations or communities that experienced the strongest structural damage.

Remaining Challenges
Negros Power acknowledged that a small portion of households continued to wait for electricity due to conditions that required more complex interventions. These challenges included:
- Downed poles in isolated sitios that required manual transport and installation
- Severe damage to meters and overhead service wires
- Privately owned poles and transformers that needed formal agreements before reconnection
- Houses with unrepaired service entrances caused by storm-related destruction
Despite these obstacles, the utility assured consumers that field personnel were working continuously to complete the remaining tasks, prioritizing both safety and efficiency.
Strength in Community Cooperation
Beyond technical capability, officials highlighted how the recovery was made possible through strong collaboration. Government agencies, barangay leaders, volunteers, and partner organizations all provided manpower and logistical support, significantly accelerating restoration timelines.
The collective effort, recognized by Secretary Garin, was described as a clear demonstration of the Bayanihan spirit — a defining value that once again emerged in the face of adversity.
Continued Commitment to Recovery
The progress achieved within three weeks reflects the dedication of linemen, engineers, support staff, and community partners working together toward a common goal. Negros Power reiterated its commitment to completing the remaining restoration activities and supporting affected residents as they rebuild normalcy in their homes and communities.
As Central Negros moves forward from Typhoon Tino’s aftermath, the swift restoration of electricity stands as a reminder of what can be accomplished when public and private sectors unite for the common good.





